Customer: Lower Murray Water
To improve operator safe access, a new water-tight submarine door was designed and installed at ground level into the existing water treatment Clarifier side wall.
Customer: Lower Murray Water
To improve operator safe access, a new water-tight submarine door was designed and installed at ground level into the existing water treatment Clarifier side wall.
Customer: Corangamite Catchment Management Authority
Decommissioning of redundant penstock gates. Design, manufacture and installation of new penstock gates as required replacing the decommissioned gates.
Customer: Coliban Water
Design, manufacture and installation of automated hydraulic trash grate system for the purpose of hydraulically lifting flotsam debris out of the water transmission channel.
Customer: Lower Murray Water
Fabrication and construction of a new stainless steel Flow Splitter Box and above ground DN750 Rising Main together with associated outlet pipe work and valves for the upgrade of the raw water treatment process at the Mildura 7th St treatment plant.
Customer: Southern Rural Water
Fabrication and Installation of an Auxiliary Valve system at Glenmaggie dam, to allow Southern Rural Water finer control of the irrigation water flow.
Customer: Sun Water
In order enable safe access to the rising main thrust block / flexible bend and pontoon anchorage Pad on the Eungella Dam.
Customer: Sun Water
The pump station consists of a reinforced concrete dry well approximately 8.0 metres in diameter and 30.0 metres in height. The pump station is subjected to the regular flooding of the Bowen River.
Customer: State Water
Fabrication of replacement support trusses for the weir gates and design, fabrication and installation of a new walkway at Redbank Weir, on the Murrumbidgee River.
Customer: City West Water
The work involved the decommissioning and removal of an unused elevated water storage tower at Manor Lakes. All infrastructure was dismantled and removed, included the storage tank and tower, concrete footings and electrical control systems.
Customer: Leed / John Holland JV
Fabrication of MSCL pipe fittings from 100mm Diameter up to 1m Diameter for Adelaide water infrastructure upgrade. Fittings included manifolds, tees, bends and dismantling joints.
Customer: Southern Rural Water
Fabrication and Installation of walkways and testing trolley to provide access to various anchor head locations at Southern Rural Water’s Glenmaggie Dam
Customer: Central Highland Water
The wastewater pumping station required upgrading to meet current and future flow requirements. This included a wide range of flows with significant delivery heads at peak flow conditions.
Customer: City of Port Adelaide Enfield
The project consisted of the demolition of an old overhead gantry and flooring over the top of a pump station pit.
Customer: Southern Rural Water
Installation of the 2 slipmeters at the Cowwarr Offtake included the Design & Supply of 1 temporary bulkhead to isolate the offtake channel. Demolition and removal of part of cover slab on pits and removal of existing gate and equipment.
Customer: Southern Rural Water
Replacement of the existing DN700 Ductile Iron main outlet conduit at Melton reservoir Vic with a new DN900 Mild Steel Cement Lined (MSCL) outlet conduit, as the existing conduit had exceed its design life.
Customer: SA Water
The varied standards of ladders, working platforms, guard railings and hatches on SA Water Above Ground tanks were an unacceptable risk to SA Water staff.
Customer: Fenner Dunlop
Design, fabrication and installation of 2 Rotocure Roll Aligners. The large rubber conveyor belt roll was being manually lined up with the Rotocure using the overhead crane and Portapower hydraulic jacks.
Customer: Southern Rural Water
Fabrication and Installation of new Weir Structure access Staircase for Cowwarr Weir. Fabrication and Installation of new weir structure gantry crane maintenance access stairs and platforms.
Customer: Barwon Water Alliance
Uptime Services were engaged by Barwon Water Alliance to upgrade the existing Barwon Heads Sewage Pump Station # 1. The upgrade works included construction of a new concrete valve pit and slab lid over the existing well.
Customer: Port of Melbourne
The work involved supply and install of a packaged Xylem Pump Station including the new pump and control systems, installing the existing flowrate into the new pit, design and install shoring during the works.
Customer: Murray Irrigation
Fabrication, paint, delivery, installation and adjustment of new side panels and removal of existing side panels at various regulators over a 4-year period on the Mulwala canal.
Customer: SA Water
Design, Manufacture and installation of access walkways, stairs and ladders for valve chambers located at SA Water pumping stations.
Customer: Alcoa
Design, Fabrication and Installation on a ship unloader boom for Alcoa. The ship unloader boom is used to unload Bauxite from the transport ship for the Port Henry Aluminium Smelter.